Skip to navigation Skip to main content

 

Click here to access Norwegian translation

Introduction

Norway has significant potential to lead the way for green hydrogen and green ammonia production, based on availability of renewable energy, proximity to the European market, and skilled workforce. In partnership with local Norwegian consultants, Fortescue has completed a Scoping Study to identify potential locations for production of green hydrogen and ammonia. Consideration has been given to a range of factors, such as existing grid and power capacity, proximity to existing infrastructure, land availability, water sources, topography, and the local environment and surrounding communities.

Through these investigations, and in consultation with the Bremanger Municipality, the Holmaneset project opportunity was identified.

 

What is the Holmaneset Project?

The proposed Holmaneset Project seeks to utilise surplus renewable energy to power an integrated green hydrogen and green ammonia process plant, complete with transmission infrastructure and port facilities, for the transport of green products to the Norwegian and European markets. It is located on the coast of the Nordgulen fjord, approximately 8 kilometres west of Svelgen in the Bremanger Municipality in western Norway.

 

The Holmaneset Project is located on the coast of the Nordgulen fjord, approximately 8 kilometres west of Svelgen in the Bremanger Municipality in western Norway.

In March 2023, Fortescue entered into a  long-term Power Purchase Agreement (PPA) with Statkraft. The Project is progressing through the  Feasibility Phase with many activities currently being undertaken in parallel to refine the Project layout with consideration of environmental, social and safety factors to determine potential impacts, and attain the necessary regulatory permits to progress.

The primary activities being undertaken at current is a planning process for the area and early engineering and design works, including geotechnical (e.g. rock fall and avalanche risks) and other ground investigations. These activities are further described below – Activities Underway. In undertaking these activities, Fortescue is in dialogue with relevant authorities and regulatory bodies on a local, regional and national level.

 

Proposed Project Description

  • It is expected that the Holmaneset site will contain administrative offices, warehouses, access control and fencing, hydrogen electrolysis, ammonia synthesis, ammonia tank for storage, transformer station, flare tower for safety purposes and two port facilities: one for the transport of ammonia and a traditional quay facility for transporting materials and equipment.
  • The footprint, layout and size of these Project components, including the storage tank and safety flare tower, are not yet finalised and will be modified through future engineering and design work. Feedback from environmental and social studies will be used to inform final specifications and area use. Based on feedback from Stakeholders, Fortescue is revising layouts to minimise impacts on areas identified as having high ecological value. Preliminary design layouts will be shared with local stakeholders and applicable authorities once available.
  • Preliminary estimates indicate 35 to 70 jobs directly linked to production at Holmaneset. In addition, there will be indirect employment opportunities through the contracting of local suppliers to perform services, such as cleaning and maintenance.
  • Depending on the final ship size and guidance from the Coastal Authority on safe ship navigation, the Project expects to require one to four ships per month once in operation.
  • Power is planned to be supplied to the site from the Svelgen substation.
  • Transmission infrastructure will be required to transport power and water to the Holmaneset site. Fortescue is assessing corridors with consideration of environmental, social and safety factors. Both subsea and terrestrial options are being considered and local stakeholders will be engaged as plans progress.
  • Preliminary environmental and geotechnical site surveys have taken place since 2022 to inform early engineering and design works and capture seasonal variation for the impact assessment.
  • Fortescue is targeting the commencement of the Construction Phase in 2025, with the start of Operations in 2027. These targeted timeframes may change depending on the time it takes to go through the regulatory approvals process as well as technical and commercial preparations.

 

Production Process

Hydrogen produced through electrolysis of water and powered by renewable energy is emission-free and referred to as green hydrogen. Electrolysis is achieved by passing electricity through demineralized water so that the water is split into green hydrogen and oxygen. The oxygen produced is not toxic. It is completely odorless and tasteless – and can be used for other purposes (industry or other).

The hydrogen will then be converted into ammonia by combining nitrogen from the air with the green hydrogen to create green ammonia. This is done for easier and safer storage and transportation of the green energy. Ammonia has been produced, stored and transported for hundreds of years by industry for use in agriculture as fertiliser, a refrigerant gas, for purification of water supplies and in the manufacture of plastics, textiles, dyes, and other chemicals.

Green Ammonia in a refrigerated state is planned to be transported to the Norwegian and European markets by ship to support the decarbonisation of hard to abate sectors such as heavy haulage, shipping, fertilizer and industry. Further information on green hydrogen and ammonia production processes, manufacturing and safety is available below.

Additionally, production of ammonia and hydrogen creates oxygen and heat as by-products, which can be used in other industry, such as aquaculture, water treatment, metals refining and fabrication processes, and glass, ceramic and paper manufacturing. Where practical, waste heat from the process will be recovered and reused at the facility, and the Project will aim to develop other opportunities to support a green energy circular economy.

 

Activities Underway

As mentioned above, there are a number of activities underway that are supporting the development of the Project design and the understanding of the potential positive and negative impacts. Key activities currently underway include:

  • Planning Process, which is the process used to formally rezone the land for industrial purposes within the Municipality and involves the undertaking of an Environmental Impact Assessment. This activity is being undertaken by Rambøll (and Henning Larson, a Ramboll Group Company) a global engineering, architecture and consultancy company with a long history of operating in Norway.
  • Early engineering and design works, which is being done to develop a technically feasible, safe and reliable plant design, which meets Norwegian regulatory requirements as well as Fortescue's own rigorous project assurance guidelines. This activity is being undertaken by Norconsult a Norwegian engineering, architecture and consultancy company.
  • Site investigations to characterise the conditions at the Project site. These include mapping of the seabed around the Holmaneset peninsula and Nordgulen Fjord, nearshore and onshore geotechnical and geophysical sampling and testing, water quality monitoring, and measurement of metocean conditions.

These parallel activities are tightly intertwined with an iterative process occurring between the planning process and design of the Project – for example, where environmental sensitivities and concerns are identified in the Planning Process, efforts will be made through engineering to modify the design as needed to minimise negative or enhance positive impacts.

 

The Planning Process

The Planning Process for the area zoning was initiated in February 2023 in cooperation with the Bremanger Municipality. The planning area covers 1349 daa. This includes the Holmaneset peninsula, and the three islands of Litleholmen, Meholmen and Storeholmen.

The Planning Process is carried out in accordance with the Planning and Building Act, and is, among other things, subject to requirements for:

  • Public inspection and participation
  • Impact assessment
  • Risk and vulnerability analysis

The first step in the Planning Process is to develop a Planning Program that describes which topics and alternatives are to be investigated and examined before the preparation of a Planning Proposal. The Planning Program underwent a 6-week public consultation in May-June 2023. Feedback received from interested parties, including the local community and authorities, will be taken into consideration, and addressed prior to presenting the Planning Program to the municipality council for approval.

Once the Planning Program has been approved, the regulatory process leads to a Planning Proposal. During this phase a comprehensive assessment of environmental, societal and safety risks will be undertaken to inform the Planning Proposal and ensure decision-makers have the necessary information to decide on the rezoning of the area for industrial use. These studies and assessments are expected to take about one year. 

The Planning Program is available in Project Document section below.

 

Impact Assessment Process

An impact assessment is an obligatory part of the Planning Proposal. This is a complete assessment of the Project’s impact on the environment and society. The impact assessment follows a methodology that assesses and analyses the value and impact the Project has on natural diversity, water environment, landscape, outdoor life, cultural environment, society impacts, natural resources and pollution (noise, light, vibrations, air, water and ground) in accordance with the Norwegian Environment Agency’s guide M-1941.

These investigations are based on existing knowledge from the area and are supplemented with field surveys and sampling. This information is then used to inform the Planning Proposal which is subject to public review prior to approval of the new area zoning. 

In addition to complying with Norwegian regulations, Fortescue has expanded the spectrum of assessments to be undertaken to align with international standards that outline good practice for managing environmental and social impacts, including the International Finance Corporation’s Performance Standards, Equator Principals and Green Hydrogen standard.

 

Safety

The health and safety of our people, including contractors and suppliers, and the communities in which we operate are Fortescue's highest priority. Fortescue is in dialogue with DSB and will undertake a number of safety assessments as the Project progresses. These will be  undertaken by an independent, reputable company in accordance with EU and Norwegian regulations.

The safety assessments will seek to identify hazards relating to project processes, such as storage units, operation procedures and safety elements, including shutdown procedures, to define potential safety concerns This will then be used to develop gas dispersion models with consideration of external factors, such weather conditions, to assess potential safety risk to workers and surrounding communities. These studies will be undertaken over longer periods of time. 

These risk and safety assessments will be undertaken in parallel with the risk and vulnerability assessment, which is part of the Planning Process. The risk and vulnerability assessment provides a systematic approach to identifying and evaluating potential threats and impacts the Project may cause to the area. The assessment methodology is described in the DSB’s guide – ‘Social security in the municipality’s spatial planning.’

Documentation of the methodology and findings in the risk assessment will be shared with relevant authorities, and the findings captured in the Planning Process. In the end, it is the DSB, under the Fire and Explosion Prevention Act, that is the responsible national authority for granting permission, firstly to start construction, and finally for permission to operate a hydrogen and ammonia facility at Holmaneset.

 

Project Benefits

Green industry development is a priority for Norway and Europe. The Norwegian Government’s Hydrogen Strategy (2020) emphasizes both the national and international importance for the kind of production that is planned at Holmaneset. The production of green hydrogen will contribute to the path to a low-emission society, and it is also a step in the right direction to reduce greenhouse gas emissions globally.

The McKinsey report “Norway Tomorrow” points out that Norway has a competitive advantage for the production of blue and green hydrogen with the potential to create 36,000 new jobs and contribute to a value creation of NOK 71 billion until 2030. A successful national strategy for hydrogen production could contribute to an emissions reduction of 22 million tonnes of Co2 in Norway and Europe.

Fortescue recognises the significant potential for Norway to lead the way for green hydrogen and green ammonia production based on availability of renewable energy, proximity to the European market, and skilled workforce. Through the Holmaneset Project we hope to develop a local, regional and national value chain for green industry that contributes to increased employment, business and training opportunities – with a focus on the Bremanger Municipality and the region.

To support this development, Fortescue has prepared a Local Content Plan in consultation with local and regional government bodies, business associations and educational institutions. We recognise the need to commence this early to give individuals and businesses the time to prepare in order to maximise the benefits of such an opportunity. The aim of this Plan is to ensure we maximise opportunities for local training, recruitment and provision of goods and services, by ensuring clear channels of communication.

Fortescue aims to build a long-term presence in Svelgen and the region and wants to be a positive contributor to the local community. Updates on the project plans will be published on the website on an ongoing basis but if you have any specific questions, please contact us.

 

Contact

For further information on the Holmaneset Project, please contact us at Norway@Fortescue.com

 

We're leading the green industrial revolution

We’re developing the technologies to decarbonise hard-to-abate sectors (like our iron ore operations) while building a global portfolio of renewable energy projects.

Green iron and green steel presents a huge opportunity for the iron ore industry and we are working hard to ensure we are at the forefront of technologies being developed in this regard.

By harnessing the world’s renewable energy resources to produce renewable electricity, green hydrogen, green ammonia and other green industrial products, we’ll help our planet step beyond fossil fuels.

  • Green hydrogen
  • Green steel
  • Critical minerals
  • Solar power
  • Green ammonia
  • Hydropower
  • Wind energy
  • Geothermal energy